As of July 9, the south abutment footing for the future bridge over the Little Devil Track River is complete. Crews will move to driving pile for the north abutment footing this week.
Construction activity will continue to be focused at the future bridge in the next 4 – 6 weeks with the completion of the north abutment footing as well as the north and south abutments and wing walls.
Beams are scheduled to be set in the early Fall, and roadway construction will begin in the early Fall as well.
We would like to thank the traveling public for their patience and cooperation while the road is reduced to a single lane at the temporary bridge.