Project 61: Hwy 61 in Grand Marais: 2020-2021 Construction Update
Jul 16, 2021 11:33AM ● By EditorFrom the Minnesota Department of Transportation - July 16, 2021
On Hwy 61, the contractor has been paving mainline in Phases 2A and 2C, which are between 3rd Ave W and Broadway, and the lake side of Hwy 61 between 8th and 3rd Ave W, respectively. Concrete curb and gutter and sidewalk/pedestrian ramp work has been installed in these areas as well. Finish grading and temporary erosion control will follow until sodding dates resume.
Currently, construction is on the northbound (or lake) side of Hwy 61 between 8th Ave W and 3rd Ave W. Starting Monday, July 19, the work will begin on the southbound (or inland) side of Hwy 61. The single lane of northbound Hwy 61 traffic in this area will shift from the inland side of Hwy 61 to the lake side of the road.
Work is nearing completion between on Phase 2A at 3rd Ave W and Broadway Ave, signs and striping are being installed this week. On July 21 or 22, that section will reopen to traffic.
Please contact us with any questions.
Important reminders for motorists regarding work zone safety:
- Slow down when approaching every work zone, then navigate through with care and caution.
- Stay alert; work zones constantly change.
- Watch for workers and slow moving equipment.
- Obey posted speed limits. Fine for a violation in a work zone is $300.
- Minimize distractions behind the wheel.
- Be patient; expect delays, especially during peak travel times.
For more information on projects in northeast Minnesota, follow us on Facebook at https://facebook.com/groups/MnDOTnortheast and Twitter at @mndotnortheast. For real-time traffic and travel information in Minnesota, visit www.511mn.org.
To stay informed on North Shore construction projects, follow this link to the Project 61 updates page by following this link. https://www.boreal.org/pages/welcome-to-the-project-61-update-page